We have completed completed our design and gathered our materials. We are a bit behind in design construction, but we have simultaneously started putting together our final presentation. We will meet and finish both tasks this Sunday at 2pm.
Friday, November 19, 2010
Thursday, November 11, 2010
Project #2, Blog #3
Today, Project Panda discussed our project, which ironically is not about Pandas. It is about Liberia.
Topics for today included:
- Electricity needed to power a germicide lamp
- Math to determine the electricity needed to power a germicide lamp.
> We would need about 300 pounds of water to power a germicide lamp using a turbine with a 3in radius to produce about 3 gallons/min. We have decide to use a different method of water purification.
- Alternative water purification options
> Sedimentation is a common and inexpensive way to filter water that does not require any electricity.
- Alterations to project design
> We will use a downspout filter similar to a Brita design and store any power created by the turbine in a battery to be used for emergency power.
- Prototype construction
> A non-working prototype will most likely be created as a working prototype would be too expensive for our budget.
- Next meeting: Sunday, November, 14, 2010; order of business: Prototype material purchase and construction
Yamani doesn't like people named Jack.
Jonathan likes bacon.
Topics for today included:
- Electricity needed to power a germicide lamp
- Math to determine the electricity needed to power a germicide lamp.
> We would need about 300 pounds of water to power a germicide lamp using a turbine with a 3in radius to produce about 3 gallons/min. We have decide to use a different method of water purification.
- Alternative water purification options
> Sedimentation is a common and inexpensive way to filter water that does not require any electricity.
- Alterations to project design
> We will use a downspout filter similar to a Brita design and store any power created by the turbine in a battery to be used for emergency power.
- Prototype construction
> A non-working prototype will most likely be created as a working prototype would be too expensive for our budget.
- Next meeting: Sunday, November, 14, 2010; order of business: Prototype material purchase and construction
Yamani doesn't like people named Jack.
Jonathan likes bacon.
Wednesday, November 3, 2010
Project #2, Blog #2: Materials
Today we met at 7pm to discuss the materials we will use to build our prototype. This discussion led to our discovering many holes in our design. We made a list of topics to research which we will come back to tomorrow in class. Meeting dismissed at 8:40pm.
Below is the Gantt Chart we updated for today.
Gantt Chart - November 3, 2010
Below is the Gantt Chart we updated for today.
Gantt Chart - November 3, 2010